天泰書院康(kang)城(cheng)項目位(wei)于淄博市經開區海(hai)岱大道與南西五路(lu)交叉口(kou),總建筑(zhu)面積(ji)18萬平方米,分為(wei)一期(qi)和二期(qi)兩個標段(duan),海川建設(she)承建的天泰書院康城二期(qi)項目總建筑面積10.05萬平方米,項目包含1#樓至(zhi)11#樓11棟住宅及S1商(shang)業、S2商(shang)業、門衛(物業)等(deng)建筑。地上建筑面(mian)積為(wei)77974.7㎡,地下建筑面積22567.39㎡;地上2-18層,地下1-2層;框架、剪力墻結構。1#樓是兩個標段首(shou)棟封(feng)頂(ding)的樓座。
該項(xiang)目(mu)建設單位于3月(yue)16日取得施(shi)工許(xu)可證(zheng),接受(shou)第一批(pi)1#、8#樓基槽,開始清槽,正式進場施工。建設單位要求首批1#樓4月(yue)15日完(wan)成一(yi)層結構(gou)(gou)施(shi)工(gong)(gong);8#樓4月(yue)20日完(wan)成2層結構(gou)(gou)施(shi)工(gong)(gong),達到預售(shou)節點,工(gong)(gong)期緊(jin)、任務(wu)重(zhong),從清槽(cao)至2層結構封頂,工期僅36天時間。進場伊始,項目部(bu)精心(xin)組(zu)織(zhi)施(shi)工(gong)(gong)(gong),科學編制施(shi)工(gong)(gong)(gong)進度計劃,合(he)理安(an)排工(gong)(gong)(gong)序穿插(cha),協(xie)調(diao)分包單位克服困難,保證工(gong)(gong)(gong)人數量,保證施(shi)工(gong)(gong)(gong)所需(xu)材料供應及(ji)時,人員可休息機(ji)械(xie)不能停,組(zu)織(zhi)晝夜搶工(gong)(gong)(gong)。通過日(ri)清會,項目部(bu)積極協(xie)調(diao)土方(fang)、降水、樁基(ji)、支護等專業分包單位按照我單位的(de)施(shi)工(gong)(gong)(gong)節奏提供工(gong)(gong)(gong)作面,避(bi)免(mian)交叉(cha)作業相互制約,從(cong)而保證了施(shi)工(gong)(gong)(gong)進度。1#樓(lou)從3月19日(ri)驗槽完成開始墊層澆筑(zhu)至5月19日6層結構封頂,歷時兩個月。項目部在施工進度上跑除了加速度,得到了建設單位的好評。在封頂儀式上,建設單位向項目部贈送了錦旗:“求真務實講效率,爭分奪秒搶工期”,對項目施工進度給予認可。